Project

Finchampstead

Client

Cala Homes

Scope

Amet Contracting Group successfully executed a sustainable topsoil redistribution project in Finchampstead in 2024, showcasing innovation, cost savings and environmental gains.

  • Remove 10,000m3 of topsoil from the site
  • Find a sustainable solution for the excess material
  • Ensure compliance with material movement regulations
  • Minimus project costs and environmental impact

Cost Savings

Our innovative approach saved the client approximately £250,000 by re-using the topsoil locally instead of sending it to landfill

Environmental Gains

By redistributing the topsoil locally, the project reduced carbon emissions assocaited with long-distance transportation.

Safety Compliance

Navigated complex on-site logistics & implemented safety measures whilst ensuring full compliance with MMP requirements

Amet’s tailored solution:

  • Tested the soil and found it was suitable for re-use
  • Utilised our extensive network to identify sites in the local area in need of topsoil
  • Discovered that the site directly neighbouring our site needed topsoil for their Public Open Space areas
  • Our team coordinated with all stakeholders, including the client, earthworks contractor, and environmental consultants, to facilitate a direct transfer of materials between the two sites.
  • Material Management Plans were completed for both sites to ensure compliance
  • Used Moxy articulated dumpers, operating on a carefully planned route that prioritised safety and efficiency across the two sites. This included strategically placed banksmen, one-way traffic procedures, and a live communication system to ensure smooth and safe operations.